GSoC 2023: Flamenco Improvements

GSoC Week 7 Report

First mid-term has passed. Many thanks to my mentor for all his help and guidance :partying_face:. But, it’s not over yet, and I still have a ways to go.

Accomplishments:

For this week, it was relatively slow with the starting the new task and trying to complete the previous worker clusters task.

  • Issue Worker Tags for clustering #104204 is another step closer to being finished and Flamenco version 3.3 being released!
  • Created PR for Web interface: fetch version on SocketIO reconnect (and maybe reload) #99410. I hope for it to be fully finished this week.

Struggles / Blockers

The biggest blocker I faced was trying to figure out where to start with issue #99410 as there seemed to be some parts that I was not familiar with. However, thanks to the well written documentation for Flamenco, I found a starting point and was able to start the first PR! It’s nice to have the help from the community as well.

Very excited for the things to come!

3 Likes